In-plant conveyor system for a mine mouth coal fired power plant

Key Facts

Project name
Millmerran Power Project

Customer
Millmerran Power Partners

Plant location
Queensland, Australia

Commissioning
2001

Overall conveyor length
11 conveyors approx. 3,500 m overall length

Theoretical output
990 t/h to 1,980 t/h

In-plant conveyor system for a mine mouth coal fired power plant

Delivery of a complete in-plant conveyor system for a coal-fired power plant, featuring a 500-ton truck dump hopper, feeder breaker, linear stacker, portal reclaimer, and 11 belt conveyors (1,067 mm to 1,372 mm wide, totaling 3,500 m) along with transfer towers and ancillary equipment like belt scales and magnetic separators.

Would you like further information? Please contact us!

The data will be deleted once your request has been processed. You can revoke your consent at any time with future effect by sending an email to . Detailed information on how we handle your data can be found in our privacy policy on our website.

The fields marked with an asterisk * are mandatory fields!

To top